Estimated Cost: $41,785
-Clear and Grub, 1700' @ $3.75 = $6375
-Build Road, 1700' @ 5 = 8500
-Grading = 880
-Culvert, 340' @ 17 = 5780
-Rock End Section, 10 @ 230 = 2300
-Rock Rip Rap, 1400 @ 5.75 = 8050
-Seed-n-Mulch = 1000
-Stone, 6 @ 350 = 2100
-Conduit, 1500' @ 4 = 6000
-Excavation = 800
Actual Cost:
Notes: This estimate is based on a 1700' road; I'll think we'll be shorter than that at the end of the day. Includes: excavation for the foundation, the PERC test and an installed gravity septic system.