Estimated: 10,000
4500 for set crew; 5500 for crane
Actual: 11,750
4500 for set crew; 7250 for crane
Notes: We needed a bigger crane than anticipated (130 ton v. 70 ton). It seems to me as if this should have been anticipated by ALL the participants - contractor in charge of set, crane operator who gave us the initial estimate, Simplex, Res4 - but nobody questioned the smaller crane until the day of the scheduled set, when the crane operator came to set up and said no way...